Power at scale
Screen for a supply route supporting at least 10 MW of IT load; size facility demand separately using the PUE design target. Require a dated supply proposal.
Pipeline / Fact sheet
SparkDCS develops a 200 MW pipeline alongside EDIG, the land-owning platform holding sites across the UK, Spain and Poland, and brings each site to shovel-ready, starting with power availability and phased delivery.
200MW
Spain · Poland
Regional focusAt the 1.20–1.25 PUE design target, 10 MW of IT load implies 12–12.5 MW of facility demand at the same load basis.
Screen for a supply route supporting at least 10 MW of IT load; size facility demand separately using the PUE design target. Require a dated supply proposal.
Test a layout with at least two independently serviceable phases, reserving utility corridors and construction access so later works can proceed beside an operating hall.
Require two physically diverse fibre entry routes; obtain carrier route maps and test round-trip latency to the customer’s nominated major metro against its workload budget.
Require an identified heat-network counterparty and a seasonal demand study, including a feasible pipe route; compare recoverable heat against demand before sizing the export interface.
| Total development pipeline | 200 MW |
|---|---|
| Land platform | EDIG, holding the sites across the UK, Spain and Poland |
| SparkDCS role | Development to shovel-ready: power, planning, design |
| Regions | UK, Spain, Poland |
| Indicative phase scale | 10–60 MW |
| Stage detail | Available under NDA |
The IEA’s 2025 base case projects European data-centre electricity demand growing 70% from 2024 to 2030, providing the regional demand context for SparkDCS’s UK, Spain and Poland focus.
Great Britain’s transmission demand queue reached 96 GW in June 2025, according to DESNZ; SparkDCS’s power screen therefore asks for a dated supply proposal before detailed site design.